June BUILD Update

June 9, 2021

Hey Church!


Thanks so much for your continued prayers for our new facility. I am so grateful for how you are diligent to go to our Father for the sake of the world.


Here’s a summary of May’s work:

  • Completion of the asphalt pavement and striping for all parking lots and driveways.
  • Cembrit siding installations continued on the exterior of the Auditorium. 
  • Exterior GeoLam siding installation continued. 
  • The last of the drywall is being hung and finished. 
  • Ceiling grid is being installed in multiple areas of the building. 
  • The painter continued priming and applying first coats of paint to exposed ceilings, walls, doors and door frames throughout the building. 
  • Porcelain tile was installed in all restrooms.
  • The Laminam wall tile was installed in the Atrium. 
  • Sound insulation panels were installed in the Atrium. 
  • The fire protection subcontractor continued installing the sprinkler piping. 
  • The plumber started the installation of plumbing fixtures.  
  • The HVAC subcontractor completed the ductwork installations in multiple areas of the building requiring duct modifications. 
  • They also installed diffusers, transfer grilles, and VAV units throughout the building. 
  • The LVHV fans were installed in the Atrium. 
  • Electrical rough-ins, pulling wire and building panels continued throughout the building.
  • Installation of light fixtures, devices and switches continued throughout the building.