July BUILD Update

July 12, 2021

Hey Church!

Thanks so much for your continued prayers for our new facility. I am so grateful for how you are diligent to go to our Father for the sake of the world.

Here’s a summary of June’s work:

  • The respread and fine grading of the topsoil around the jobsite. 
  • The sub-flooring for the Auditorium stage was installed. 
  • Cembrit siding installations continued. 
  • Exterior GeoLam siding installations continued. 
  • Scuppers and downspouts were completed. 
  • The last of the drywall is being finished. 
  • Ceiling grid has been completed throughout the building and ceiling tile installations have begun. 
  • Interior handrails are being installed. 
  • The painter continued priming and applying first coats of paint to exposed ceilings, walls, doors and door frames throughout the building. 
  • Sound insulation panels were installed in the LP Kids areas. 
  • The fire protection subcontractor completed the sprinkler piping. 
  • The plumber installed plumbing fixtures.  
  • The HVAC subcontractor completed the ductwork re-work installations in multiple areas of the building. 
  • They also installed diffusers, transfer grilles, and VAV units throughout the building.
  • Electrical rough-ins, pulling wire and building panels continued throughout the building and the Installation of light fixtures, devices and switches continued as well.