February Build Update

February 10, 2021

Hey Church!

Thanks so much for your continued prayers for our new facility. I am so grateful for how you are diligent to go to our Father for the sake of the world.

Here’s a summary of January’s work:

  • The concrete subcontractor completed the steps in the Auditorium. 
  • The miscellaneous metal subcontractor installed the roof ladders. 
  • The roofer completed the roof coping and scuppers.  
  • The glazing subcontractor completed the last of the storefront window installations. 
  • The metal stud subcontractor continued installing interior metal stud framing in all areas of the building as well as insulating walls and hanging and finishing drywall. 
  • The siding contractor started the installation of the metal panel siding. 
  • The plumber continued rough-ins for the restrooms in the Administrative area, Lobby and LP Kids area. 
  • The fire protection subcontractor continued installing the sprinkler piping behind the stage in the Auditorium, in the Administrative Area and in the Lobby. 
  • The HVAC subcontractor continued ductwork for the rooms behind the stage in the Auditorium, in the Administrative Areas, in the Lobby and in the LP Kids area. 
  • The electrician continued electrical rough-ins throughout all areas of the building and continued building the sub-panels throughout the building.