December Build Update

December 22, 2020

Hey Church!

Thanks so much for your continued prayers for our new facility. I am so grateful for how you are diligent to go to our Father for the sake of the world.

Grace & peace,

Pastor Dean


Here’s a summary of November’s work:

  • Construction activities on site include the asphalt paving subcontractor installing the base course for the south and north parking lots.
  • The concrete subcontractor prepping and installing concrete risers and steps within the Auditorium.
  • The mason completing the block and brick for the dumpster enclosure.
  • The metal stud subcontractor completing exterior studs and sheathing for the LP Kids area, continuing the interior metal studs for the all areas and starting drywall installation.
  • The roofer installed the TPO roof for the LP Kids areas.
  • The glazing subcontractor installed window installations for the LP Kids and Atrium areas.
  • The plumber began running the gas piping for the RTUs.
  • The fire protection subcontractor started installing the sprinkler piping in the Auditorium.
  • The HVAC subcontractor set all RTUs, insulated ductwork in the Auditorium and Admin areas, and installed ductwork in the Atrium.
  • The electrician continued electrical rough-ins in the Auditorium, Administrative, Atrium, LP Kids areas and worked on getting the building energized.